SPIC Jieyang Jinghai 400MW offshore wind farm approved by local DRC

      Jieyang city DRC published a notice of approval for the SPIC Jieyang Jinghai 400MW offshore wind farm. This project is an expansion of the SPIC Jieyang Jianghai 150MW offshore wind farm. The project’s central point is 25 km from the coast, with water depths ranging between 30m and 40m.

The planned capacity of the project is 400MW, and 44 wind turbines with a single unit capacity of 12MW are planned to be installed. The total construction period of the project is 24 months, and the total investment is CNY 5.7 billion (USD 797 million).