Shanxi Energy Bureau released Shanxi’s construction plan of wind and solar competitive allocation projects in 2022, with following results:
- 10GW of new wind and solar grid connection-guaranteed projects
- 1.21GW of old projects which missed the construction deadline and are re-allocated
- 0.25GW of extra capacity given as a reward to some cities that have had a good performance during 2021
Solar projects must be fully grid-connected before the end of Sepetember,2023. Wind projects must be fully on-grid before the end of June,2024.
(BJX)